Typical Case 1
Adding ORC on a
GE Jenbacher
biogas engine
(JMS 320 GS-B.L)
- Electrical efficiency ORC: 8% - 12%
- Electricity production ORC: 50 kW + 44 kW
- Payback time: 3,8 - 4,4 years
- IRR: 19% - 23%
Typical Case 2
ORC powered by
a waste heat flow
from a chemical
process
- Tin hot = 95°C, flow rate = 10 kg / s
- Tin cold = 15°C
- Electricity production ORC = 50 kW
- Payback time: 3,4 year / IRR: 27 %
Important remark: Payback times and IRRs caculated without ecology
grants! Payback from 2,5 years and IRR above 30% easily feasible!